Stormwater Management Permit
This is intended to be a general summary of the application process. Variations may occur. For specific details, refer to the
Post-Construction Administrative Manual.
Required for development and/or redevelopment activities.
Issued by Mecklenburg County Land Development in coordination with the jurisdiction.
Governs the design, installation, and construction of stormwater management and control practices on the site, including structural Best Management Practices (BMPs).
Without a permit, each day of a continuing violation constitutes a separate offense and an additional fine of up to $5,000 per day.
Steps for Permit and Plan Review
Concept Plan
Pre-submittal or Pre-resubmittal meetings required for Concept Plans. Please refer to the
Town & County Plan Intake Checklist for specifics.
A Land Development Application must be filled out electronically and uploaded into the Electronic Plan Management (
EPM) system. Additionally, the following items should be included where applicable:
Plans and calculations (must be sealed by professional designer)
Address verification form signed by County GIS Department
Traffic Impact Study/Analysis (TIS/TIA)
Fee payment submitted with first submittal
Follow the
Plan Review Checklist.
As part of the Concept Plan application, the applicant can request an optional consultation meeting with staff.
Applicants can request an exemption from buffer requirements on certain stream buffers shown on
POLARIS. Use the
Stream Reach Evaluation Form to request the exemption.
Mitigation options are not offered in the Town of Cornelius.
Stormwater Management Permit (SWMP)
Pre-submittal or Pre-resubmittal meetings required for Storm Water Management Permit. Please refer to
Town & County Plan Intake Checklist for specifics.
A Land Development application must be filled out electronically and uploaded with the following into the Electronic Plan Management (
EPM) system:
Design Procedure Form for each BMP (if applicable)
BMP Maintenance Covenant and Plan* (if applicable) - *Submit documents into the Electronic Plan Management (
EPM) system for review. Following approval, these documents must be recorded at the Mecklenburg County Register of Deeds Office and a copy of the recorded documents uploaded into the EPM system during the SWMP review and plat review stages.
Staff will review the Permit Application and associated submittals within 21 calendar days. Submittals that do not comply will be returned with "redlines." According to Post Construction regulations, the applicant has 60 calendar days to resubmit their corrected plan submittal or otherwise face starting all over with additional fees.
As project plans are approved in the Electronic Plan Management (
EPM) system, electronic stamps are placed on the plans and the applicant receives an email with an approval letter from Mecklenburg County
stating the next steps to take and, if applicable, an NPDES Packet (if grading > 1 acre). Electronically approved stamped plans are then available for downloading and printing.
Permit Issuance/Pre-Construction Conference
The Stormwater Management Permit will be issued following approval of plans and applications.
Once the applicant has received the Permit, it is valid for three years or until construction is completed.
After the Permit has been issued, staff will initiate and conduct a pre-construction conference.
Construction, Inspections and Plats
Staff will conduct on-site inspections during development and/or construction.
Written notice will be issued for site deficiencies.
Submit final plats and associated easements into the Electronic Management Plan (
EPM) system for review and approval.
Following approval, the plats and easements must be recorded at the Mecklenburg County Register of Deeds Office and an electronic copy of the recorded plat emailed to the County Plat Reviewer to upload into the Electronic Management Plan (
EPM) system.
Stormwater Bonds and Certificates of Occupancy
A BMP Installation Bond (Performance Bond) must be submitted if a Certificate of Occupancy is needed prior to the completion of the Stormwater Management structure(s).
A two-year
BMP Maintenance Bond must be submitted prior to the final approval and release of the project.
Final Inspection and Approval of BMPs
After construction of required BMPs, an as-built survey must be prepared in accordance with the
As-Built Checklist.
An engineering certification must be prepared by the applicant's design engineer declaring that the BMPs are in compliance with previously-approved plans.
Follow the
Compliance Checklist.
Submit completed as-builts through
EPM (Electronic Plan Management system).
Staff will review the documents and perform an inspection of the project site for compliance with all Post-Construction Ordinance (PCO) requirements including BMP installation.
Long-Term BMP Maintenance
All BMPs must be inspected annually by a registered professional engineer or landscape architect within one year of receipt of as-built approval.
Submit the completed
BMP Maintenance and Inspection Checklist for each BMP within two weeks following completion of the inspection and any associated maintenance activities.
Please note a transfer of BMP maintenance is not allowed in the Town of Cornelius.
Submit the BMP Maintenance and Inspection Checklist to:
Mecklenburg County
Land Use & Environment Services Agency
Permitting and Compliance Program
2145 Suttle Ave.
Charlotte, NC 28208
Attn: Heather Davis
Appeals and Variances
An appeal may be initiated by any aggrieved person affected by any decision, order, requirement or determination relating to the interpretation or application of the Post-Construction Stormwater Ordinance (PCO), including penalty assessment.
A
Request for Appeal form must be submitted to Mecklenburg County.
A variance from the Ordinance requirements may be requested by submitting a
Petition for Variance to Mecklenburg County.
Submit forms and documents to:
Mecklenburg County
Land Use & Environment Services Agency
Water Quality Program
2145 Suttle Ave.
Charlotte, NC 28208
Attn: Stormwater Administrator