Wanamassa Storm Drainage Improvement Project

​Lat​est News

  
Update
3/23/2020

​The project construction phase is complete.  The project warranty phase begins for one year.

​Overview

The Wanamassa Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 60 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. 

Estimated Cost: $3,500,000​​*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process. Learn more about project phases.

​Map

​Sched​ule

  
  
  
PlanningCOMPLETEDJune 2015
DesignCOMPLETEDJuly 2018
PermittingCOMPLETEDJuly 2018
Property Easement/AcquisitionCOMPLETEDJuly 2018
BidCOMPLETEDNovember 2018
ConstructionCOMPLETEDMarch 2020
WarrantyIN PROGRESSMarch 2021

​Proje​ct Team

Steven Brown

Construction Inspector

Michelle Montgomery

Construction Supervisor

Willia​m Harris, EI

Project Manager

​Mul​timedia

​Docu​ments

  
  
Wanamassa December 2019 Mailer.pdfWanamassa December 2019 Mailer
Wanamassa February 2019 Mailer.pdfWanamassa February 2019 Mailer
Wanamassa February 2018 Mailer.pdfWanamassa February 2018 Mailer
Wanamassa July 2016 Mailer.pdfWanamassa July 2016 Mailer
Wanamassa June 2016 Mailer.pdfWanamassa June 2016 Mailer
Wanamassa August 2015 Mailer.pdfWanamassa August 2015 Mailer
Wanamassa April 2015 Mailer.pdfWanamassa April 2015 Mailer
Wanamassa December 2014 Mailer.pdfWanamassa December 2014 Mailer
Wanamassa November 2014 Mailer.pdfWanamassa November 2014 Mailer
Wanamassa June 2014 Mailer.pdfWanamassa June 2014 Mailer
Wanamassa May 2014 Mailer.pdfWanamassa May 2014 Mailer
Wanamassa March 2014 Mailer.pdfWanamassa March 2014 Mailer
Wanamassa November 2013 Mailer.pdfWanamassa November 2013 Mailer