Stewart Creek Tributary 2 Greenway and Stream Enhancement

Project is in the construction phase.

Overview

The Stewart Creek Tributary 2 Greenway and Stream Enhancement Project will improve creek banks to reduce erosion and sediment. Construction is scheduled to start in March and is anticipated to take eight months.

Objectives:

  • Repair Eroding Stream Banks
  • Improve Water Quality
  • Improve Habitat
  • Reduce the amount of sediment in the water
  • *This project WILL NOT reduce flooding

Estimated Cost: $175,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

Map

Please use the latest versions of Google Chrome, Mozilla Firefox, Apple Safari, or Microsoft Edge to view the map.

​Schedule

  
  
  
PlanningCOMPLETEDMarch 2019
DesignCOMPLETEDOctober 2019
PermittingCOMPLETEDOctober 2019
Property Easement/AcquisitionIN PROGRESS
BidCOMPLETEDNovember 2021
ConstructionIN PROGRESS
WarrantyTBD

​Project Team

Stephanie Roberts-Bowman, PE

Project Manager