Storm Water Services will perform steam and wetland restoration from I-485 to the South Carolina State Line to improve water quality and reduce erosion.

Project Phase: 90% Engineering Plans Due May 2017

Project Engineer: Kimley-Horn and Associates

Project Features: Greenway

Status:
Construction on hold, waiting for final easements.

Cost:
$3.2 million 

Outreach:
Construction plan was shared at community meeting in September 2017
​​
Map

Schedule

  
  
  
PlanningTBD
DesignTBD
PermittingTBD
Property Easement/AcquisitionTBD
BidTBD
ConstructionON HOLD
WarrantyTBD