Project Phase: 90% Engineering Plans Due May 2017

Project Engineer: Kimley-Horn and Associates

Project Features: Greenway

Status:
Construction on hold, waiting for final easements.

Cost:
$3.2 million 

Outreach:
Construction plan was shared at community meeting in September 2017
​​
Map
Current Conditions

Project Manager

Stephanie Roberts-Bowman, P.E.
980-314-3239​​​​