Projects

​Little Sugar Creek Polk Street to Stateline​

Project is in the bid phase.

Overview 

Storm Water Services will perform steam and wetland restoration from I-485 to the South Carolina State Line to improve water quality and reduce erosion.

Estimated Cost: $3.2 million* 

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process. Learn more about project phases.

Map

Please use the latest versions of Google Chrome, Mozilla Firefox, Apple Safari, or Microsoft Edge to view the map.

Schedule

  
  
  
PlanningCOMPLETEDJune 2016
DesignCOMPLETEDDecember 2018
PermittingCOMPLETEDDecember 2018
Property Easement/AcquisitionCOMPLETEDDecember 2019
BidIN PROGRESS
ConstructionTBD
WarrantyTBD

​Project Team 

Stephanie Roberts-Bowman, PE

Project Manager

Current conditions before project construction.