Projects

​Lilly ​Mill Storm Drainage Improvement Project

Project is in the construction phase.

​Latest ​News

  
Update
9/3/2020

Park Road has two new pedestrian refuges between Park South Drive and Sharon Road! When crossing the street, refuges provide pedestrians the opportunity to stop safely in the center turn lane and cross one direction of traffic at a time. Charlotte-Mecklenburg Storm Water Services collaborated with Charlotte Department of Transportation on this new roadway feature. 

The contractor has completed most of the work on Park Road and will soon focus on the remaining sanitary sewer crossings. Sanitary sewer lines often cross streams posing a threat to water quality. Since several of the crossings were at the end of their useful life, Charlotte Water and Charlotte-Mecklenburg Storm Water Services collaborated on making repairs where needed to proactively prevent sanitary sewer spills in our waterways.

Over​view

The Sunnyvale/Chandworth Storm Drainage Improvement Project, with a drainage area of 640 acres, was broken down into three smaller projects: Lilly Mill, Chandworth and Tattersall.

The Lilly Mill Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood and address stream erosion to provide a more natural, stable stream system.  Located within a drainage area of approximately 100 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity.

Estimated Cost: $11,800,000​*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process. Learn more about project phases.

Map

​Schedul​e

  
  
  
PlanningCOMPLETEDJanuary 2013
DesignCOMPLETEDJuly 2018
PermittingCOMPLETEDJuly 2018
Property Easement/AcquisitionCOMPLETEDDecember 2016
BidCOMPLETEDMay 2018
ConstructionIN PROGRESSAnticipated March 2021
WarrantyTBD

​Proje​ct Team

Jimmy Knight

Construction Inspector

Edrina​ Maben-Collins

Senior Construction Inspector

Adam Clapp

Construction Supervisor

Jackie Bray, PE

Senior ​Project Manager

​Mu​ltimedia

​Do​cuments

  
  
Lilly Mill May 2020 Mailer.pdfLilly Mill May 2020 Mailer
Lilly Mill March 2020 Mailer.pdfLilly Mill March 2020 Mailer
Lilly Mill July 2019 Mailer.pdfLilly Mill July 2019 Mailer
Lilly Mill November 2018 Mailer.pdfLilly Mill November 2018 Mailer
Lilly Mill May 2018 Mailer.pdfLilly Mill May 2018 Mailer
Lilly Mill March 2018 Mailer.pdfLilly Mill March 2018 Mailer
Lilly Mill January 2017 Mailer.pdfLilly Mill January 2017 Mailer
Lilly Mill June 2016 Mailer.pdfLilly Mill June 2016 Mailer
Lilly Mill November 2015 Mailer.pdfLilly Mill November 2015 Mailer
Lilly Mill July 2015 Mailer.pdfLilly Mill July 2015 Mailer
Lilly Mill March 2015 Mailer.pdfLilly Mill March 2015 Mailer
Lilly Mill November 2014 Mailer.pdfLilly Mill November 2014 Mailer
Lilly Mill July 2014 Mailer.pdfLilly Mill July 2014 Mailer
Lilly Mill June 12 2014 Public Meeting Presentation.pdfLilly Mill June 12 2014 Public Meeting Presentation
Lilly Mill June 12 2014 Public Meeting Minutes.pdfLilly Mill June 12 2014 Public Meeting Minutes
Lilly Mill May 2014 Mailer.pdfLilly Mill May 2014 Mailer
Lilly Mill March 2014 Mailer.pdfLilly Mill March 2014 Mailer
Lilly Mill November 2013 Mailer.pdfLilly Mill November 2013 Mailer