Projects

​K​enilworth/Romany​ Storm Drainage Improvement Project

Project is in the construction phase.

​Project Updates

  
Update
11/9/2021

​Work is again underway in the Kenilworth/Scott Avenue and Romany Road intersection. View the November mailer for more information.

7/27/2021

Kenilworth/Scott Ave. and Romany Rd. intersection work is underway. As work progresses across the intersection from the hospital campus along Romany Rd., we will continue to coordinate traffic flow with the Charlotte Department of Transportation. Detours, road and lane closures will be ongoing in the Kenilworth/Scott Ave. and Romany Rd. intersection until late fall. To ensure the safety of motorists, pedestrians and crew, please follow all signs. View the July mailer for more information.

​O​verview  

The K​enilworth/Romany​ Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 233 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. 

The project is bordered by Berkely Avenue to the north, East Boulevard to the west, Buchanan Street to the south and Morehead Street to the east. Streets in the project area include Romany Road, Scott Avenue, Kenilworth Avenue, Waverly Avenue, Buchanan Street, Linganore Place, and Dilworth Road.  

Estimated Cost: $21,800,000​​*

*includes all costs associated with the project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process. Learn more about project phases.

Map​​

Please use the latest versions of Google Chrome, Mozilla Firefox, Apple Safari, or Microsoft Edge to view the map.

​​Schedule

  
  
  
PlanningCOMPLETEDApril 2013
DesignCOMPLETEDJuly 2019
PermittingCOMPLETEDJuly 2019
Property Easement/AcquisitionCOMPLETEDJuly 2019
BidCOMPLETEDMarch 2020
ConstructionIN PROGRESSAnticipated September 2022
WarrantyTBD

Proje​ct Team​

Avery Braun

Senior Construction Inspector

Emely Robles-Saravia

Construction Inspector

Adam Clapp

Construction Supervisor

Chad Nussman

Senior Project Manager

Tyler Howell, PE

Project Manager​

Videos

View the Public Meeting Recording from the February 18, 2021 meeting.

​D​ocuments

  
  
Kenilworth November 2021.pdfKenilworth November 2021
Kenilworth July 2021.pdfKenilworth July 2021
Kenilworth March 2021 Virtual Public Meeting Minutes.pdfKenilworth March 2021 Virtual Public Meeting Minutes
Kenilworth February 2021 Public Meeting Notice.pdfKenilworth February 2021 Public Meeting Notice
Kenilworth October 2020 Mailer.pdfKenilworth October 2020 Mailer
Kenilworth April 2020 Mailer.pdfKenilworth April 2020 Mailer
Kenilworth November 2015 Mailer.pdfKenilworth November 2015 Mailer
Kenilworth July 2015 Mailer.pdfKenilworth July 2015 Mailer
Kenilworth March 2015 Mailer.pdfKenilworth March 2015 Mailer
Kenilworth November 2014 Mailer.pdfKenilworth November 2014 Mailer
Kenilworth October 2014 Mailer.pdfKenilworth October 2014 Mailer
Kenilworth July 2014 Mailer.pdfKenilworth July 2014 Mailer
Kenilworth March 2014 Mailer.pdfKenilworth March 2014 Mailer
Kenilworth November 2013 Mailer.pdfKenilworth November 2013 Mailer
Kenilworth July 2013 Mailer.pdfKenilworth July 2013 Mailer
Kenilworth March 2013 Mailer.pdfKenilworth March 2013 Mailer
Kenilworth October 2012 Mailer.pdfKenilworth October 2012 Mailer
Kenilworth June 2012 Mailer.pdfKenilworth June 2012 Mailer
Kenilworth February 2012 Mailer.pdfKenilworth February 2012 Mailer
Kenilworth January 2012 Mailer.pdfKenilworth January 2012 Mailer
Kenilworth September 2011 Mailer.pdfKenilworth September 2011 Mailer
Kenilworth May 2011 Mailer.pdfKenilworth May 2011 Mailer
Kenilworth February 2011 Mailer.pdfKenilworth February 2011 Mailer
Kenilworth Questionnaire.pdfKenilworth Questionnaire