​K​enilworth/Romany​ Storm Drainage Improvement Project
​Lat​est News
  
Update
4/21/2020

Construction is underway. View the latest mailer for more information.

​O​verview  

The K​enilworth/Romany​ Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 233 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. The project is bordered by Berkely Avenue to the north, East Boulevard to the west, Buchanan Street to the south and Morehead Street to the east. Streets in the project area include Romany Road, Scott Avenue, Kenilworth Avenue, Waverly Avenue, Buchanan Street, Linganore Place, and Dilworth Road.  

Estimated Cost: $21,800,000​​*
*includes all costs associated with the project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and general descriptions with timeframes are below. Public involvement is emphasized throughout the process.

Map​​

​​Schedule

  
  
  
PlanningCOMPLETEDApril 2013
DesignCOMPLETEDJuly 2019
PermittingCOMPLETEDJuly 2019
Property Easement/AcquisitionCOMPLETEDJuly 2019
BidCOMPLETEDMarch 2020
ConstructionIN PROGRESSAnticipated September 2022
WarrantyTBD

Proje​ct Team​


Avery Braun
Construction Inspector
704-619-6984
Avery.Braun@CharlotteNC.gov

Geno Bernhard
Construction Inspector
704-780-2214
EBernhard@CharlotteNC.gov

Adam Clapp
Construction Supervisor
704-634-5062
AClapp@CharlotteNC.gov

Senior Project Manager
704-336-5676 
CNussman@CharlotteNC.gov 

Tyler Howell, PE

Project Manager​
​980-293-2931 ​
Tyler.Howell@CharlotteNC.gov

​Mu​ltimedia

​D​ocuments

  
  
Kenilworth April 2020 Mailer.pdfKenilworth April 2020 Mailer
Kenilworth November 2015 Mailer.pdfKenilworth November 2015 Mailer
Kenilworth July 2015 Mailer.pdfKenilworth July 2015 Mailer
Kenilworth March 2015 Mailer.pdfKenilworth March 2015 Mailer
Kenilworth November 2014 Mailer.pdfKenilworth November 2014 Mailer
Kenilworth October 2014 Mailer.pdfKenilworth October 2014 Mailer
Kenilworth July 2014 Mailer.pdfKenilworth July 2014 Mailer
Kenilworth March 2014 Mailer.pdfKenilworth March 2014 Mailer
Kenilworth November 2013 Mailer.pdfKenilworth November 2013 Mailer
Kenilworth July 2013 Mailer.pdfKenilworth July 2013 Mailer
Kenilworth March 2013 Mailer.pdfKenilworth March 2013 Mailer
Kenilworth October 2012 Mailer.pdfKenilworth October 2012 Mailer
Kenilworth June 2012 Mailer.pdfKenilworth June 2012 Mailer
Kenilworth February 2012 Mailer.pdfKenilworth February 2012 Mailer
Kenilworth January 2012 Mailer.pdfKenilworth January 2012 Mailer
1 - 15Next

​​​​​​​​​​​​​​​​​​​​​​​Project Phases  ​

​​Planning
Survey crews document the existing drainage system and surrounding areas. The project team uses this information, along with property owner input and requests for service, to analyze existing drainage system conditions. Staff hosts a public meeting to present the existing conditions analysis and obtain additional input from property owners. Several improvement alternatives are then developed and evaluated to determine the most economical and least impactful solution. The project team presents the recommended alternative to property owners for input at a public meeting at the end of this phase. This phase typically lasts 12 to 27 months.

Design
The project team develops detailed construction drawings for the selected alternative, addressing pipe sizes and alignments, drainage channel widths, utility relocations and easement locations. A project team member may meet with individual property owners to discuss the drainage system improvements and how construction will impact specific properties. The project team hosts a public meeting to present the preliminary design plan, which illustrates specific improvements to properties, and begin the easement acquisition process. This phase typically lasts 21 to 34 months.

​Permitting
The project team obtains required Federal and State water quality permits and other necessary permits, such as permission to work within railroad and NCDOT rights-of-way, as necessary. This phase typically lasts 3 to 9 months and will overlap with the Design Phase.

Property Easement/Acquisition
Staff works with property owners to acquire ​​temporary or permanent easements. Easements provide permission for Storm Water Services to access the property, construct the recommended improvement and provide future maintenance. This phase typically lasts 9 to 12 months and will overlap with the Design Phase.

Bid
A competitive bidding process is held to select a qualified contractor to construct the project. By state law, the lowest responsible bidder is awarded the construction contract. This phase typically lasts 7 to 8 months.

Construction
Throughout construction, the project team works to minimize disruption to property owners. The Storm Water Services construction inspector serves as the main point of contact for residents. Notifications of key construction dates will be communicated to residents prior to construction.  This phase varies, depending on the specific project, but typically lasts up to two years.

Warranty
The construction contract includes a warranty guaranteeing materials and workmanship for one year from the date of completion. The construction inspector conducts 6- and 11-month inspections during the warranty period. Upon notification, the contractor must repair defective items at no additional cost. 

​​​