Projects

​Eaglewood Storm Drainage Improvement Project

Project is in the bid phase.

​Latest News

  
Update
There are no items to show in this view of the "Project updates" list.

Overview

This project involves analysis of existing conditions to determine portions of the storm drainage system suitable for improvement, planning analysis of improvement alternatives and the design and construction of the needed improvements.

The Eaglewood Storm Drainage Improvement Project is bordered by Wallace Road to the north and east, Woodberry road to the south and Pinafore Drive to the west. The project is within a drainage area of approximately 65 acres and the improvements may include system replacement primarily within the Eaglewood Avenue right-of-way.​

Estimated Cost: $3,500,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process. Learn more about project phases.

Map

Please use the latest versions of Google Chrome, Mozilla Firefox, Apple Safari, or Microsoft Edge to view the map.

​Schedule

  
  
  
PlanningCOMPLETEDApril 2019
DesignCOMPLETEDFebruary 2021
PermittingCOMPLETEDFebruary 2021
Property Easement/AcquisitionCOMPLETEDJune 2020
BidIN PROGRESSAnticipated April 2021
ConstructionTBD
WarrantyTBD

Project Team

Brian Wilson, PE

Project Manager

Amy Bice, EI

Watershed Area Manager

Matthew Gustis, PE

Engineering Program Manager