Projects

Ce​lia Avenue Storm Drainage Improvement Project

​Latest News 

  
Update
There are no items to show in this view of the "Project updates" list.

Over​view

The Celia Avenue Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. The project is located within a drainage area of approximately 48 acres.   

Estimated Cost: $1,500,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and general descriptions with timeframes are below. Public involvement is emphasized throughout the process. 

​Map​

​Schedul​e 

  
  
  
PlanningCOMPLETEDMarch 2012
Property Easement/AcquisitionPhase 1 September 2012, Phase 2 April 2013Phase 1 July 2013, Phase 2 April 2014
DesignCOMPLETEDSeptember 2014
PermittingCOMPLETEDJune 2014
BidCOMPLETEDSeptember 2014
ConstructionCOMPLETEDJuly 2015
WarrantyCOMPLETEDJuly 2016

Project Team


Matthew Gustis, PE
Engineering Program Manager
704-336-6183​
mgustis@charlottenc.gov

​Multime​dia

​Docu​ments

  
  
There are no items to show in this view of the "Documents" document library.
a​​​​​​​​​​​​​​​​​​​​​​​​​Project Phases   ​