Sunview/Telfair Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Sunview/Telfair Storm Drainage Improvement Project involves analysis of existing conditions to determine portions of the storm drainage system needing improvement, planning analysis of improvement alternatives, and design and construction of needed improvements. The project is located within a drainage area of approximately 146 acres. The project area is bordered by Archdale Drive to the north, Old Reid Road to the south, Park Road to the east and Old Reid Road to the west.

Project Updates

October 2024

Charlotte-Mecklenburg Storm Water Services is working with LandDesign, Geoscience Group, and CES Group Engineers to evaluate a culvert and the storm drainage system in this area. 

Representatives may need to enter your property to perform utility soft digs, geotechnical borings, and to collect data on the existing system. While state law authorizes access to private property, no building or structure will be entered.

The work is scheduled to begin in October and take about 2 months to complete.

                

Estimated Cost: To Be Determined*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Planning

Learn more about project phases.