Cutchin Drive​ Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Cutchin Drive Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 160 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. The project area is bordered by Sharon View Road to the north, Wamath Drive and Mountainbrook Road to the south, McMullen Creek to the east and Sharon Road to the west.

Project Updates

July 2024

Construction of the Cutchin Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase. The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs. 

Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.

        

Estimated Cost: $10,400,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Warranty

Learn more about project phases.


Schedule
Phase Status End Date
Planning Completed June 2016
Design Completed March 2021
Permitting Completed November 2020
Property Easement/Acquisition Completed May 2019
Bid Completed August 2021
Construction Completed June 2024
Warranty In Progress June 2025