Chan​dworth Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Chandworth Storm Drainage Improvement Project will replace aging infrastructure plus reduce street and structure flooding throughout the neighborhood. The project is located within a drainage area of approximately 200 acres. The project area is bordered by Sulkirk Road to the north, Ashton Drive and Riverbend Road to the south, Tyndale Avenue and Rhodes Avenue to the east and Park Road to the west.

Project Updates

December 2023

Construction of the Chandworth Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase. The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs.

Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.

    

Estimated Cost: $11,100,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Warranty

Learn more about project phases.


Schedule
Phase Status End Date
Planning Completed November 2013
Design Completed June 2020
Permitting Completed September 2019
Property Easement/Acquisition Completed April 2019
Bid Completed December 2020
Construction Completed September 2023
Warranty In Progress n/a