7th Street / Monroe Road project is complete from Washburn to Fannie Circle, except for the final paving. Heitkamp, the contractor is working between Fannie Circle and Ranier Avenue February 1 through April.
Woodruff (in Wesley Heights) started in February and be complete in April. There will be minimal traffic impacts on Woodruff and no streets will be closed. Temporary lane closures only.
Randolph Road at Caswell will start in April and be complete in May or early June. Randolph Road will have temporary lane closures but maintaining 2-way traffic flow.
Cherry neighborhood will start after May. Additional information is available here.