Taggart Creek Sewer Outfall Project

​​​​​​

Project phase

 

 Project updates

  • ​The Taggart Creek Outfall Project is located in West Charlotte and generally runs parallel to Billy Graham Parkway.  The project will provide for replacement of aging infrastructure.  Approximately 17,000 linear feet of new 36" and 42" diameter sewers will replace the old, undersized lines. 
  • Twenty properties are directly affected by this project, most of which are business developments.​

​​Properties that will be directly affected by construction have been contacted and all easements and permits obtained.  Construction notification letters have also been sent.​

​$18.8 M construction cost

 

 Project contacts