Construction can be loud, dirty, and inconvenient. Crews will be using large machinery and storing materials within construction easements on site.

  • Clearing - Trees, shrubs, and other vegetation within the 30-foot wide construction easement area will be removed. Debris will be transported off-site or tuned into mulch.
  • Pipe delivery and storage – Pipes and other equipment are delivered and stored within the construction easements.
  • Establishing a safe work zone – Fencing will be put in place and pipe will be stabilized to prevent it from moving.
  • Trench digging.
  • Crews will tunnel under Sam Newell Road.
  • Placing pipe and backfilling.
  • Customers may feel a rumble (Video)
    • Crews may remove rock formations by blasting or rock hammers.
      • Property owners within the 500-foot radius of blast sites were contacted in advance and offered a pre-blast survey.
      • Blasting is a standard construction procedure and all safety precautions will be taken.
      • Residents may hear a warning horn and feel a slight vibration or rumble similar to a slammed door or thunder.
    • Blasting will be conducted as needed between 9:00 a.m. and 5:00 p.m.
      • Expect most blasts will be scheduled in the afternoon.

Construction traffic (excavators, dump trucks) in the easements and road right-of-way. Once the pipe is installed near your property, you may continue to see construction traffic along the easements until the pipe is tested, manholes are adjusted and restoration is complete.​

  • Installing gravity sewer to serve residents along a tributary of Irvins Creek.  
  • To design the optimal route for this project, engineers have taken many factors into account including engineering specifications, human and environmental impacts, regulatory requirements, and budget. 

​Properties that will be directly affected by construction will be contacted to discuss easement agreements. Areas near construction will be notified before construction begins. 