Charlotte Water and Blue Granite Water Company Drinking Water Interconnection Project
Project phase

 

 Project updates

​Charlotte Water will install pipe to connect to Blue Granite Water Company (BGWC) near the Buster Boyd Bridge on York Road in South Carolina. This important interconnection will provide BGWC with additional​ water to serve the area.
  • Construction start: mid-August
  • Construction completion: November
  • Normal work hours: 7:00 am – 7:00 pm, Monday through Friday.
    • Contractor will work nights and weekends only as needed.
  • Staff will notify affected customers of planned water outages 72-hours in advance.
    • ​Any unplanned water outages are considered emergencies and will be repaired as soon as possible.
  • Photo book of water and wastewater construction
  • Updates will be posted on this website.

​Project will enhance water capacity and pressure.​

​Areas near construction will be notified before construction. There will be planned water outages to move customer’s service. Property owners will be notified in advance. If there is an unplanned water outage, crews will work to fix it immediately.​

​TBD​

 