Hartley Street Water Pipe Replacement Project

​​​​

Project phase

 

 Project updates

  • The project started on August 8th and may last 45 days.
  • Approximately 600 linear feet of 2-inch galvanized steel pipe [GSP] water main will be abandoned and replaced with 400 feet of 2-inch PVC water main and 160 feet of 6-inch Ductile Iron Pipe (DIP). 
  • All existing services will be renewed.
  • Staff will notify affected customers of planned water outages 72-hours in advance.
  • Any unplanned water outages are considered emergencies and will be repaired as soon as possible.
  • Construction may cause temporary cloudy, discolored water or lower than usual pressure. If you experience this, please run cold water for up to 15 minutes. If water doesn't clear, please call 311 and say or select 'water emergency' for assistance.
  • The project​ includes restoration of affected sidewalks and roadways
  • CLTWater works with CDOT and NCDOT to minimize traffic disruption. CDOT permitted road closures are posted on the CDOT's website.
  • Updates will be posted on this website and NextDoor.
  • Lane closures may be required daily in coordination with CDOT. 

  • CLTWater will replace the pipe under the street that is past its useful life.
  • The project will enhance water quality and pressure.

 