| | North Bridge Over Interstate 85 | Yes | CIP standalone project | 3/31/2023 | General Services | North Bridge Over Interstate 85 | The bridge project is being value engineered and re-designed to reduce
construction cost. The project team will review and follow steps
for approval of the re-design, including approval from NCDOT. Once the
re-design is approved the project will go through the re-bidding process. The
duct bank contractor is 90% complete with utility fiber tie-ins. The contractor
will next start pulling fiber through the duct bank. Once the fiber pulling is
complete, utility companies will begin splicing fiber for utility cut overs.
Relocating utility infrastructure must be completed by the utility companies
before roadway construction can start in this area. Because of the complex
nature of the work, utility relocation can be a lengthy process. Our goal is to
perform this work while keeping workers safe and maintaining access for
commuters and surrounding businesses. Please obey all regulatory and
informational signage to ensure everyone's safety.
| 3/31/2023 11:09 AM | 3/31/2023 11:11 AM | Behlke, Kristen | 1.0 | Completed | Completed | 2291 |
| | Brown-Grier Road upgrades | Yes | CNIP - Whitehall/Ayrsley | 3/30/2023 | General Services | Brown-Grier Road upgrades | Design and
real estate acquisition is 95 percent complete. The city continues to work diligently
to secure the remaining two parcels in the project limits before utility
relocation can start along Brown-Grier Road. The project team will proceed to
the bid phase once all parcels have been secured. During the bid phase, the
city uses a competitive bidding process to procure the services of a contractor
to build the project. By state law, the contract is awarded to the lowest
responsible bidder. An update on the start of the bid phase will be shared once
it is determined.
| 3/30/2023 1:26 PM | 3/30/2023 1:28 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2290 |
| | DeArmon Road complete street improvements | Yes | CNIP - Prosperity Village | 3/29/2023 | General Services | DeArmon Road complete street improvements | The project team is pleased to announce the project received federal
funding to complete construction of the entire road. Before construction can
begin, a tree clearing contractor will be hired to make way for the utility
companies to relocate their facilities. Tree clearing is anticipated to occur
in late summer and then the utility companies will begin relocating later in
the year.
| 3/29/2023 12:12 PM | 3/29/2023 3:38 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2289 |
| | Central/Kilborne/Norland pedestrian improvements | Yes | CNIP - Central/Albemarle/Shamrock | 3/29/2023 | General Services | Central/Kilborne/Norland pedestrian improvements | The project has been placed on temporary hold due to recent inflation. The project team will review the overall project scope and budget to determine what improvements can be constructed. Utility relocation is currently in progress.
| 3/29/2023 12:09 PM | 3/29/2023 12:10 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2288 |
| | Newell South neighborhood improvement phase 2 | Yes | CIP standalone project | 3/28/2023 | General Services | Newell South neighborhood improvement phase 2 | Construction for this project completed in December 2022 and is now in the warranty phase. During the warranty phase, periodic field inspections will be conducted to identify any items that may need repaired. The city appreciates your patience during construction of this unique project.
| 3/28/2023 8:24 PM | 3/28/2023 8:25 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2287 |
| | Brett Court, Afternoon Court, Clendon Court, and Shoup Court Water Main Replacement | Yes | | 3/28/2023 | Water | Brett Court, Afternoon Court, Clendon Court, and Shoup Court Water Main Replacement | Starting the week of April 3rd, Charlotte Water (CLTWater) and contractors, Dallas 1, will start construction to replace existing water pipes. Construction will take at least two months.
| 3/28/2023 10:03 AM | 3/28/2023 10:35 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2284 |
| | Berry Tree Court Water Main Replacement | Yes | | 3/27/2023 | Water | Berry Tree Court Water Main Replacement | Starting the week of March 27th, Charlotte Water (CLTWater) and contractors, Dallas 1, will start construction to replace existing water pipes. Construction will take at least two months.
Construction can be loud, dirty and inconvenient. Crews will reduce disruptions where possible. Crews will be using heavy equipment and storing materials on-site. Construction will take place in and beside the roadway within the right-of-way. Please be aware of your surroundings near the construction site and report any safety concerns to the project inspector as soon as possible.
| 3/28/2023 10:07 AM | 3/28/2023 10:34 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2285 |
| | Dixie Berryhill Drinking Water Project - from Sadler Road to Berewick Elementary School | Yes | | 3/28/2023 | Water | Dixie Berryhill Drinking Water Project - from Sadler Road to Berewick Elementary School | Charlotte Water (CLTWater) will extend drinking water pipes along Dixie River Road from the 5900 block of Dixie River Road to Sadler Road. Clearing of the easement will begin late March and water pipe construction is scheduled to start in June 2023.
| 3/28/2023 10:13 AM | 3/28/2023 10:34 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2286 |
| | Little Hope Creek Wastewater Improvement Project | Yes | | 3/28/2023 | Water | Little Hope Creek Wastewater Improvement Project | A section of Hartford Avenue between Shawnee Drive and Annlin Avenue is expected to be closed starting March 28. Construction is expected to be complete by the end of the week.
During this time, motorists should follow all detour signage and use Annlin Avenue to Hollis Road to Hartford Avenue. Access will be maintained for residents that live within the impacted construction zone.
Please note construction schedules are subject to change due to weather and other conditions.

| 3/28/2023 8:48 AM | 3/28/2023 8:50 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2283 |
| | Idlewild, Rama and Monroe intersection | Yes | East/Southeast Corridor | 3/27/2023 | General Services | Idlewild, Rama and Monroe intersection | This project is currently in the utility relocation phase. During this
phase, utility infrastructure, such as underground gas, water and sewer lines,
as well as overhead power, telephone and television lines, will be moved as
needed to make way for construction. Construction is expected to begin in fall
2024.
| 3/27/2023 6:26 PM | 3/27/2023 6:27 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2282 |
| | Shamrock Drive Complete Street | Yes | CNIP - Central/Albemarle/Shamrock | 3/27/2023 | General Services | Shamrock Drive Complete Street | The Shamrock Drive Pop-Up
Dog Park will be removed this spring. This temporary dog park was opened
in summer 2019 as a short-term amenity in advance of the Shamrock Drive
Complete Street and Shamrock Drive Storm Drainage Improvement Project. As the
projects move closer to the Utility Relocation Phase, it is time to remove the
dog park in advance of this work. Storm Water Services will be constructing a
stormwater control measure in this location to capture, clean and slowly
release rain water. Construction expected to start in mid-2024.
| 3/27/2023 12:32 PM | 3/27/2023 12:33 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2281 |
| | Morris Field Drive bridge replacement | Yes | Bridge repair | 3/21/2023 | General Services | Morris Field Drive bridge replacement | Private utility companies are working on the means and methods to start relocating overhead and/or underground utilities. This process can take several months. Once utility relocation is complete, the project is expected to go out to bid in 2024. During the bid phase, the city uses a competitive bidding process to procure the services of a contractor to build the improvements identified during the design phase. By state law, the construction contract is awarded to the lowest responsible bidder.
| 3/21/2023 4:33 PM | 3/21/2023 4:35 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2280 |
| | Sherwood Forest Water Pipe Replacement | Yes | | 3/16/2023 | Water | Sherwood Forest Water Pipe Replacement | Starting the week of April 3rd, Charlotte Water (CLTWater) and contractor, HG&L, will start construction to replace existing water pipes under Nottingham Drive (Addison Drive to Robinhood Road and Mansfield Avenue to end of the street), Grosner Place, and Deveron Drive (King Edward Road to the end of the street). Construction is estimated to take four months to complete.
| 3/16/2023 9:21 PM | 3/16/2023 9:23 PM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2279 |
| | Westinghouse Boulevard Multi-Use Path | Yes | CNIP - Whitehall/Ayrsley | 3/15/2023 | General Services | Westinghouse Boulevard Multi-Use Path | Construction continues. The contractor is installing drainage improvements and grading in areas in advance of installing the multi-use path. The mulit-use path has been installed in some areas. The project is expected to be complete by the end of 2023.
| 3/15/2023 4:19 PM | 3/15/2023 4:25 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2278 |
| | Monroe Road streetscape | Yes | East/Southeast Corridor | 3/10/2023 | General Services | Monroe Road streetscape | This project is now in the utility relocation phase. During this phase, utility infrastructure, such as underground gas, water and sewer lines, as well as overhead power, telephone and television lines, are moved as needed to make way for construction for the project improvements. Construction is expected to begin in early 2025.
| 3/10/2023 6:48 PM | 3/10/2023 6:50 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2277 |
| | Clarke Creek Pump Station and Force Main Project | Yes | | 3/10/2023 | Water | Clarke Creek Pump Station and Force Main Project | | 3/10/2023 5:09 PM | 3/10/2023 5:11 PM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2276 |
| | McAlpine Creek Wastewater Rehabilitation Project - Post Ridge Court to Smoke Tree Lane | Yes | | 3/9/2023 | Water | McAlpine Creek Wastewater Rehabilitation Project - Post Ridge Court to Smoke Tree Lane | Charlotte
Water (CLTWater) is completing the design and will not advertise this
project to bid until a later date. We will update you once the project is
scheduled.
| 3/9/2023 6:05 PM | 3/9/2023 6:06 PM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2275 |
| | River District Firehouse | Yes | | 3/7/2023 | General Services | River District Firehouse | VIRTUAL PUBLIC MEETING March 28, 2023 at 6 p.m. via Zoom
Meeting ID: 872 6949 3979 Passcode: 447241
Join by phone at 919-205-6099 or 301-715-8592 For those unable to attend live, a recording will be made available afterward.
The project team will host a virtual public meeting to share information about the project and next steps. For those unable to attend, a recording will be made available afterward.
| 3/7/2023 10:38 AM | 3/7/2023 5:31 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2274 |
| | 16th Street Streetscape Phase 2 | Yes | Applied Innovation Corridor | 12/8/2022 | General Services | 16th Street Streetscape Phase 2 | The city is working with
Norfolk Southern Railroad to acquire right-of-way to install the remaining
sidewalk on 16th Street. Once the parcel is acquired, the sidewalk work will
progress to the bid phase. During the bid phase, the city uses a competitive
bidding process to procure the services of a contractor to build the project.
By state law, the construction contract is awarded to the lowest responsible
bidder.
| 12/8/2022 2:18 PM | 3/7/2023 1:26 PM | Warren, Tabitha | 1.0 | Completed | | 2227 |
| | Rail Trail Bridge | Yes | | 3/6/2023 | General Services | Rail Trail Bridge | The real estate acquisition phase is winding down. Last year's 90% design plan and estimate submission revealed that inflation had affected the pricing of several major materials required for construction. After further investigation of the hostile bid environment, the decision was made to take the project through various value engineering exercises to bring the project's cost estimate down to better align with the project's budget. The design team is currently preparing the plans for a 100% submission in the coming month and then start the bid process later this year in 2023. Construction is expected to start in 2024.
| 3/6/2023 4:10 PM | 3/6/2023 4:12 PM | Warren, Tabitha | 1.0 | Completed | Completed | 2273 |
| | North Tryon and 36th Streetscape | Yes | NECI - Northeast Corridor | 3/6/2023 | General Services | North Tryon and 36th Streetscape | | 7/19/2022 1:01 PM | 3/6/2023 3:44 PM | Warren, Tabitha | 1.0 | Completed | | 2090 |
| | Cross Charlotte Trail Segment 06 - Matheson Avenue to East Craighead Road | Yes | XCLT | 3/6/2023 | General Services | Cross Charlotte Trail Segment 06 - Matheson Avenue to East Craighead Road | Design continues for this
segment of the Cross Charlotte Trail. The city is coordinating the design of this segment
with Norfolk Southern Railroad and other local stakeholders to complete 90%
design plans. Real estate acquisition will begin once 90% plans are complete.
| 7/19/2022 1:05 PM | 3/6/2023 3:42 PM | Warren, Tabitha | 1.0 | Completed | | 2091 |
| | Hidden Valley Water System Improvements | Yes | | 2/28/2023 | Water | Hidden Valley Water System Improvements | Current and Upcoming Work (Next 90 days) - Crews will continue to work along Tom Hunter Road at North Tryon Street.
- Residents and businesses will see varying levels of construction on Tom Hunter Road between North Tryon Street and Log Cabin Road. Construction is expected to be ongoing through the summer.
- Crews are checking and replacing water valves along the project route, which requires temporary water service interruptions. If your property is impacted, you will be notified several days in advance with the exact day and time of the planned outage, which is expected to last up to two (2) hours.
| 2/28/2023 9:11 AM | 2/28/2023 9:13 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2272 |
| | Toby Creek Sanitary Sewer Improvement Project Phase II and III | Yes | | 2/28/2023 | Water | Toby Creek Sanitary Sewer Improvement Project Phase II and III | - Charlotte Water (CLTWater) is currently in the design phase of the Toby Creek Sanitary Sewer Improvement Project. The design phase is expected to end in October 2023.
After the design phase, construction is anticipated to begin in Summer 2025. During the design phase, some properties have been identified for a potential permanent easement or temporary construction easement agreement along the proposed project route. Those property owners have been contacted directly by CLTWater. Land acquired through easements will be used to build and maintain the required sewer pipes for this project. An easement allows CLTWater to use part of a property owner's land after a legal agreement has been reached. This includes the right to access, maintain, clear, repair, inspect, improve, renovate and replace facilities in the easement. CLTWater will work with individual property owners to finalize the terms of the agreement. Beginning in March 2023, CLTWater's representatives, TELICS, will be in contact with individual property owners to set up a time to discuss the easement process and the next steps at their convenience.
| 2/24/2023 4:53 PM | 2/28/2023 8:25 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2271 |
| | Six Mile Creek Tributary - Southhampton Commons to Six Mile Creek Wastewater Pipe Enhancement | Yes | | 2/16/2023 | Water | Six Mile Creek Tributary - Southhampton Commons to Six Mile Creek Wastewater Pipe Enhancement | During March and April, Charlotte Water (CLTWater) authorized contractors, ESP, Catawba Valley Engineering & Testing (CVET), and Big Foot Forestry, will clear debris and conduct subsurface investigations (also known as test pit or soft dig, similar to photograph on to the right) to assess soil and rock conditions along the pipe alignment. Any disturbed areas will be restored. If we determine that this project will have any direct impact on your property, we will notify you further as the project progresses.
| 2/16/2023 9:51 AM | 2/16/2023 9:52 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2270 |
| | Little Hope Creek Wastewater Improvement Project | Yes | | 2/16/2023 | Water | Little Hope Creek Wastewater Improvement Project | Pipe installation and most restoration activities for phase 1 are complete. Some portions along the alignment have not been restored fully due to weather delays. Crews will be replacing grass and installing fences as needed.
Phase 2 construction began in summer 2022 and crews are moving north along the alignment. Crews are currently working behind Sewickley Drive. Phase 2 is expected to be complete in fall of 2023 and residents along the alignment will continue to see varying levels of construction.
Phases 3a and 3b design is underway with construction expected to start in late 2023. Charlotte Water and its contractors are conducting surveying and field walks along the alignment. Properties along the route that will be impacted by phase 3 construction have been, or will be, contacted by real estate representatives with Gulf Coast, LLC regarding easement acquisition.
| 2/16/2023 9:42 AM | 2/16/2023 9:44 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2269 |
| | Dave McKinney Avenue Extension | Yes | NECI - Northeast Corridor | 2/15/2023 | General Services | Dave McKinney Avenue Extension | The design phase is currently underway and plans are approximately 30 percent complete.
| 2/15/2023 1:34 PM | 2/15/2023 1:35 PM | Behlke, Kristen | 1.0 | Completed | Completed | 2268 |
| | North Davidson Street and Jordan Place Intersection | Yes | NECI - Northeast Corridor | 2/15/2023 | General Services | North Davidson Street and Jordan Place Intersection | | 2/15/2023 11:18 AM | 2/15/2023 11:19 AM | Warren, Tabitha | 1.0 | Completed | Completed | 2267 |
| | Idlewild Road Water Supply Project | Yes | | 2/3/2023 | Water | Idlewild Road Water Supply Project | This month, the Idlewild Rd Water Supply Project
team will begin construction to install a new water main along Craig Avenue in
Cotswold. To complete this work, a road closure will be put in place along
Craig Avenue on February 20, 2023 and will remain in place until December 2023.
A detour route will be available and local access will be maintained during
this time. Water service outages may occur during construction. If water outages do occur, the public can anticipate those to take place Monday—Friday, 9 am—4 pm and should not last longer than 7 hours. If a scheduled interruption is expected, residents will be notified in advance. This project is part of a wider initiative in the greater Idlewild area to enhance drinking water reliability and to ensure ongoing service for customers.
| 2/3/2023 1:52 PM | 2/15/2023 8:32 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2260 |
| | Upper Little Sugar Creek Sewer Replacement | Yes | | 2/13/2023 | Water | Upper Little Sugar Creek Sewer Replacement | Crews are nearing completion of the new storm drain culvert in Georgetown Drive. Crews will be in the middle of the street going up Georgetown Drive, Montieth Drive, and Canterwood Drive. Expect road closures and detours during this phase.
| 2/13/2023 10:20 AM | 2/13/2023 10:22 AM | Lopez Jimenez, Noilyn | 1.0 | Completed | Completed | 2266 |