September 16, 2024 - Construction is complete and the warranty phase is currently underway.
part of the Sidewalks & Pedestrian Safety Program
This project will install sidewalk and multi-use paths in three locations within the University Research Park area:
A 6-foot-wide concrete sidewalk along Medical Plaza Drive between Harris Boulevard and Mallard Creek Road
A 12-foot-wide concrete multi-use path connecting existing greenway from the intersection of David Taylor Drive and Claude Freeman Drive to the intersection of Governor Hunt Road and David Taylor Drive
A 12-foot-wide concrete multi-use path along Claude Freeman Drive from the intersection of David Taylor Drive and Claude Freeman Drive to the first business entrance at the right side of Claude Freeman Drive (10330 David Taylor Drive).
This project will also install curb ramps, pedestrian crossings, retaining walls, curb & gutter and storm drainage as needed. The total project length is .38 miles.
To increase pedestrian connectivity
To improve walkability and pedestrian safety
Patricia Abney Project Manager General Services 980.214.5845 patricia.abney@charlottenc.gov