Nov. 25, 2024 - Design for this project is 99% complete and utility relocations are underway. Advanced grading is tentatively scheduled to start this winter and the project is expected to go out for bid in early 2025.
This project will increase capacity along Rea Road by utilizing the right turn lane drops and median to develop an additional northbound and southbound through-lane along Rea Road between the ramps at I-485 and Williams Pond Lane. This project will also increase turn-lane capacity and improve the intersection at Piper Station Drive and Ballantyne Commons Parkway. Pedestrian safety and mobility will also be maintained by providing sidewalks on both sides of Rea Road. Other specific improvements include curb and gutter, accessible ramps and driveways.
To increase capacity along Rea Road
To maintain pedestrian safety and mobility
Public Involvement
The project team held a virtual public meeting in the spring of 2023 to discuss the proposed roadway improvements along Rea Road and get community feedback.
Toni Wilson Senior Engineering Project Manager General Services 704.560.6257 toni.wilson@charlottenc.gov
Joe Harper Senior Construction Inspector General Services 704.309.6181 joe.harper@charlottenc.gov
David Burke Construction Supervisor 980.556.6332 david.burke@charlottenc.gov