July 20, 2022 - Fiber optic relocation has been delayed and is expected to be complete by Aug 2022. After that construction can start on the rest of the Oakdale Road project, which must be complete before work on this project can start. Due to continued material shortages and long lead times, the estimated construction completion of the Oakdale Road FTM project is now anticipated to be mid-2023.