MS Switchgear Replacement

Closing date November 07, 2024, 03:00 PM

  • Reference numberITB AVIA 25-15
  • StatusOpen
  • SummaryBid Due Date & Time: November 7, 2024 at 3:00 PM EST.

    Bid Type: Invitation to Bid

    Department: Aviation

Description

This project is for the replacement of the existing 2500A switchboard ‘MS’ located in the basement below the main terminal of CLT airport. The existing switchgear shall be replaced with (2) new electrical distribution panelboards and shall have backup power availability through the installation of a generator docking station and manual transfer switch. The new distribution panelboards shall feed all existing circuits energized from existing switchboard ‘MS’. After all existing circuits have been refed, existing switchboard ‘MS’ shall be demolished.

Mandatory Pre-Bid Meeting and Site Visit with registration required.  See ITB package for more information and deadline to register.

 

ITB activities are facilitated through e-Builder (see "Related Information" on right-side for link).