Gold Line

​​Road Closures​​

Construction for CityLYNX Gold Line Phase 2 is slated to begin in early 2017. Until then, utility work will occur along the alignment. Road closures and project updates will be shared with affected businesses and all NotifyMe​ subscribers. Scroll to bottom of page for an interactive road closure map.

Bruns Avenue

February 15 - 24 

February 23 - March 3

South Bruns Avenue, between Duckworth Avenue and West Trade Street, will close on Wednesday, February 15, 2017 at 9 a.m. and will re-open on Friday, February 24, 2017 at 6 p.m. South Bruns Avenue, Duckworth Avenue and Wesley Heights Way should be utilized as the detour.

This closure is necessary for utility work for sewer main rehabilitation work in advance of the CityLYNX Gold Line Phase 2 project. This road will be closed to all through traffic.


 

French Street

February 20-22

French Street between Campus Street and Beatties Ford Road will close to through traffic on Monday, February 20 at 9 a.m. and will re-open on Wednesday, February 22 at 6 p.m.

There will also be daily lane shifts along Beatties Ford Road to accommodate this closure. Motorists should utilize Campus Street to Dixon Street as the detour.


 

 

Hawthorne Lane

January 23- March 6

Hawthorne Lane, between Central Avenue and Sunnyside Avenue, will close to thru traffic in both directions on Monday, January 23rd at 9:00 a.m. and will re-open on Monday, March 6th at 6:00 a.m. for sewer utility work.

Local access to residences and businesses will be maintained. The location for businesses and residents to proceed for access is designated as "Road Closed Local Traffic Only" on the map. Motorists and pedestrians should utilize Central Avenue to 7th Street. CATS will be affected.


 
 

Sunnyside Avenue

January 18 - March 6

Sunnyside Avenue, between Oakland Avenue and Hawthorne Lane, will close on Wednesday, January 18th at 9:00 a.m. and will re-open on Monday, March 6th at 6:00 a.m. for sewer utility work. Motorists and pedestrians should utilize Central Avenue to Oakland Avenue to Sunnyside Avenue for local access only.

 


 Weather and unforeseen circumstances occasionally prevent work from being completed as scheduled, and make it unsafe to reopen lanes or streets when planned. When this occurs, City traffic engineers work directly with other City staff and contractors to resolve the situation as quickly as possible and reduce impacts to the traveling public.

Pedestrians walking near work zone areas should be alert, cautious and allow extra traveling time. It is advised they cross at signalized intersections, use pedestrian walk signals where available and abide by detour signage.

Motorists traveling through work zone areas should be alert and extra cautious. Drivers should get in the correct lane well in advance and constantly be on the lookout for vehicles merging into adjacent travel lanes as they approach a work zone. Drivers should double their following distance. 

Follow the CityLYNX Gold Line Phase 2 project on Twitter @CityLYNXupdates and on Facebook atwww.Facebook.com/CityLYNXGoldLineConstructionUpdates.​

​Interactive Road Closure Map

Full details about each closure (red) and detour (green) can be found by clicking on the map. Zoom in and out to view larger map area (upper left corner of map).


Click here to open the map in a new window. You may have additional options in the basemap gallery to change the street view.