​Belmont Street & Parkwood Avenue

A new traffic signal has been approved by the Charlotte Department of Transportation for installation at the intersection of Belmont Street and Parkwood Avenue.  The signal is being installed to accommodate existing and future traffic, to provide improved pedestrian and bicycle crossings of Parkwood Avenue, and to create better traffic flow coordination.

Frequently Asked Questions

Will there be left turn arrows? 

No, the current left turn volume at the intersection does not justify the installation of left turn phases.

Will there be crosswalks and pedestrian signals? 

Yes, crosswalks and pedestrian signals will be installed for crossing all legs of the intersection.

Where is the money for the signal coming from? 

Currently, this signal is unfunded.

Will any additional road construction take place before the signal is installed? 

Yes, the median on the east leg of Parkwood will be removed to accommodate a left turn lane. 

When will the signal be operational? 

Once funding is in place, it is usually 9-12 months before the signal can be designed and installed.