Upper Torrence Creek

​Stream restoration and water quality improvements

Phase Two

Construction to begin Summer 2017

Phase Two Objectives:

County will manage the design and construction of the stream improvements on the major and minor streams: approximately 4000 linear feet of Torrence Creek and approximately 700 linear feet of an Unnamed Tributary. The project will prevent hundreds of tons of sediment annually from entering Mountain Island Lake, the primary drinking water supply for the citizens of Mecklenburg County.

Phase Two Project Budget:

  • Construction is $1.6M. Joint project with Town of Huntersville
  • $400K CWMTF grant for construction.

Phase Two Construction Schedule:

Summer 2017 to Spring 2018

Map


​​Project Team  

Phase Two Project Manager:

Brian G. Sikes
980-314-3227

Phase One Project Manager:
Crystal Taylor, P.E.
980-314-3223​​​​