Projects

Little Sugar Creek Archdale to I-485​
​Ove​rview  
This project will restore 15,522 feet of Little Sugar Creek. Mecklenburg County Asset and Facilities Management (MCA&FM) is currently working on a greenway trail design along Little Sugar Creek from Tyvola Road to the state line. A Clean Water Management Trust Fund (CWMTF) grant was submitted for a portion of this project to fund the construction of this project. The project will improve aquatic habitat and reduce in-stream erosion. 

Project Budget:
$7.5M for construction. CWMTF Grant of $400K for construction.

Project Timeline:
Construction from Summer 2017 to Fall 2018.

Project Features:
Greenway and stream joint project.

 
Map
​Projec​t Team 
Stream Restoration Project Manager:
Brian G. Sikes
Charlotte-Mecklenburg Storm Water Services
980-314-3227

Greenway Project Manager:
Karen Weston-Chien
Mecklenburg County Asset and Facility Management
980-314-2516