​Lin​coln Heights Storm Drainage Improvement Project

​Latest​ News

  
Update
8/15/2017

​A public meeting will be held on August 15, 2017 at the Beatties Ford Road Library, 2412 Beatties Ford Road.


Over​view

The Lincoln Heights Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood and address erosion to provide a more natural, stable stream system. The project is located within a drainage area of approximately 225 acres.

Estimated Cost: $5,600,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and general descriptions with timeframes are below. Public involvement is emphasized throughout the process.

Map

​Sched​ule

  
  
  
PlanningCOMPLETEDMarch 2015
DesignIN PROGRESS
PermittingTBD
Property Easement/AcquisitionTBD
BidTBD
ConstructionTBDAnticipated December 2020
WarrantyTBD

​Proje​ct Team

Steve​n McCraney
Project Manager
704-432-0967
SMcCraney@CharlotteNC.gov

Doug Lozner, PE 
Watershed Area Manager
704-432-0964 
DLozner@CharlotteNC.gov

Matthew Gustis, PE
Engineering Program Manager
704-336-6183 
MGustis@CharlotteNC​.gov​

​Multime​dia

​Docu​ments

  
  
Lincoln Heights Easement Acquisition Power Point August 15 2017.pdfLincoln Heights Easement Acquisition Power Point August 15 2017New
Lincoln Heights August 2017 Mailer.pdfLincoln Heights August 2017 Mailer
Lincoln Heights January 2017 Mailer.pdfLincoln Heights January 2017 Mailer
Lincoln Heights March 2016 Mailer.pdfLincoln Heights March 2016 Mailer
Lincoln Heights November 2015 Mailer.pdfLincoln Heights November 2015 Mailer
Lincoln Heights July 2015 Mailer.pdfLincoln Heights July 2015 Mailer
Lincoln Heights June 2015 Mailer.pdfLincoln Heights June 2015 Mailer
Lincoln Heights February 2015 Mailer.pdfLincoln Heights February 2015 Mailer
Lincoln Heights Public Meeting Minutes January 8 2015.pdfLincoln Heights Public Meeting Minutes January 8 2015
Lincoln Heights Public Meeting Presentation January 8 2015.pdfLincoln Heights Public Meeting Presentation January 8 2015
1 - 10Next

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Project Phases  

​​Planning
Survey crews document the existing drainage system and surrounding areas. The project team uses this information, along with property owner input and requests for service, to analyze existing drainage system conditions. Staff hosts a public meeting to present the existing conditions analysis and obtain additional input from property owners. Several improvement alternatives are then developed and evaluated to determine the most economical and least impactful solution. The project team presents the recommended alternative to property owners for input at a public meeting at the end of this phase. This phase typically lasts 12 to 27 months.

Design
The project team develops detailed construction drawings for the selected alternative, addressing pipe sizes and alignments, drainage channel widths, utility relocations and easement locations. A project team member may meet with individual property owners to discuss the drainage system improvements and how construction will impact specific properties. The project team hosts a public meeting to present the preliminary design plan, which illustrates specific improvements to properties, and begin the easement acquisition process. This phase typically lasts 21 to 34 months.

​Permitting
The project team obtains required Federal and State water quality permits and other necessary permits, such as permission to work within railroad and NCDOT rights-of-way, as necessary. This phase typically lasts 3 to 9 months and will overlap with the Design Phase.

Property Easement/Acquisition
Staff works with property owners to acquire ​​temporary or permanent easements. Easements provide permission for Storm Water Services to access the property, construct the recommended improvement and provide future maintenance. This phase typically lasts 9 to 12 months and will overlap with the Design Phase.

Bid
A competitive bidding process is held to select a qualified contractor to construct the project. By state law, the lowest responsible bidder is awarded the construction contract. This phase typically lasts 7 to 8 months.

Construction
Throughout construction, the project team works to minimize disruption to property owners. The Storm Water Services construction inspector serves as the main point of contact for residents. Notifications of key construction dates will be communicated to residents prior to construction.  This phase varies, depending on the specific project, but typically lasts up to two years.

Warranty
The construction contract includes a warranty guaranteeing materials and workmanship for one year from the date of completion. The construction inspector conducts 6- and 11-month inspections during the warranty period. Upon notification, the contractor must repair defective items at no additional cost.