Projects

Chan​dworth Storm Drainage Improvement Project

​Latest N​ews

  
Update
6/6/2018

Meeting Minutes and Presentation from May 24, 2018 Public Meeting

Charlotte-Mecklenburg Storm Water Services held a public meeting to present the proposed improvements and begin the easement acquisition phase.  Please see the​​ Public Meeting Minutes and Presentation​.​
5/17/2018

Public Meeting 6 p.m., Thursday May 24 at Huntingtowne Farms Elementary School

Charlotte-Mecklenburg Storm Water Services is having a public meeting to present the proposed improvements and begin the easement acquisition phase. Please join us to find out more about this project and to talk about any project-related concerns you may have. 

Over​view

The Sunnyvale/Chandworth Storm Drainage Improvement Project with a drainage area of 640 acres, was broken down into three smaller projects: Lilly Mill, Chandworth and Tattersall. 

The Chandworth Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. The project is located within a drainage area of approximately 200 acres.

Estimated Cost: $11,100,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.

The project team will manage the project through several phases. Specific work is conducted during each phase and general descriptions with timeframes are below. Public involvement is emphasized throughout the process.   

Map

​Schedu​le

  
  
  
PlanningCOMPLETEDNovember 2013
DesignIN PROGRESS
PermittingTBD
Property Easement/AcquisitionIN PROGRESS
BidTBD
ConstructionTBD
WarrantyTBD

​Proje​ct Team

Jackie Bray, PE​​
Project Manager
704-336-6770
JBray@CharlotteNC.gov

Amy Bice, EI
Watershed Area Manager
704-432-0965
ABice@CharlotteNC.gov

Matthew Gustis, PE
Engineering Program Manager
704-336-6183 
MGustis@CharlotteNC.gov​

​Multimedia

​Doc​uments

  
  
Chandworth May 24 2018 Public Meeting Presentation.pdfChandworth May 24 2018 Public Meeting Presentation
Chandworth June 2018 Mailer.pdfChandworth June 2018 Mailer
Chandworth May 2018 Mailer.pdfChandworth May 2018 Mailer
Chandworth January 2018 Mailer.pdfChandworth January 2018 Mailer
Chandworth June 2017 Mailer.pdfChandworth June 2017 Mailer
Chandworth January 2017 Mailer.pdfChandworth January 2017 Mailer
Chandworth June 2016 Mailer.pdfChandworth June 2016 Mailer
Chandworth October 2015 Mailer.pdfChandworth October 2015 Mailer
Chandworth June 2015 Mailer.pdfChandworth June 2015 Mailer
Chandworth February 2015 Mailer.pdfChandworth February 2015 Mailer
Chandworth October 2014 Mailer.pdfChandworth October 2014 Mailer
Chandworth June 2014 Mailer.pdfChandworth June 2014 Mailer
Chandworth February 2014 Mailer.pdfChandworth February 2014 Mailer
Chandworth Cctober 2013 Mailer.pdfChandworth Cctober 2013 Mailer

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Project Phases  

​​Planning
Survey crews document the existing drainage system and surrounding areas. The project team uses this information, along with property owner input and requests for service, to analyze existing drainage system conditions. Staff hosts a public meeting to present the existing conditions analysis and obtain additional input from property owners. Several improvement alternatives are then developed and evaluated to determine the most economical and least impactful solution. The project team presents the recommended alternative to property owners for input at a public meeting at the end of this phase. This phase typically lasts 12 to 27 months.

Design
The project team develops detailed construction drawings for the selected alternative, addressing pipe sizes and alignments, drainage channel widths, utility relocations and easement locations. A project team member may meet with individual property owners to discuss the drainage system improvements and how construction will impact specific properties. The project team hosts a public meeting to present the preliminary design plan, which illustrates specific improvements to properties, and begin the easement acquisition process. This phase typically lasts 21 to 34 months.

​Permitting
The project team obtains required Federal and State water quality permits and other necessary permits, such as permission to work within railroad and NCDOT rights-of-way, as necessary. This phase typically lasts 3 to 9 months and will overlap with the Design Phase.

Property Easement/Acquisition
Staff works with property owners to acquire ​​temporary or permanent easements. Easements provide permission for Storm Water Services to access the property, construct the recommended improvement and provide future maintenance. This phase typically lasts 9 to 12 months and will overlap with the Design Phase.

Bid
A competitive bidding process is held to select a qualified contractor to construct the project. By state law, the lowest responsible bidder is awarded the construction contract. This phase typically lasts 7 to 8 months.

Construction
Throughout construction, the project team works to minimize disruption to property owners. The Storm Water Services construction inspector serves as the main point of contact for residents. Notifications of key construction dates will be communicated to residents prior to construction.  This phase varies, depending on the specific project, but typically lasts up to two years.

Warranty
The construction contract includes a warranty guaranteeing materials and workmanship for one year from the date of completion. The construction inspector conducts 6- and 11-month inspections during the warranty period. Upon notification, the contractor must repair defective items at no additional cost. 


​​​