Wilmore Drive Park Avenue Sanitary Sewer Replacement

​​​​​​

Project phase

 

 Project updates

  • The current pipe is 8-inch to 15-inch in diameter and replacement pipe may be 12-inch to 30-inch- in diameter.
  • This project is anticipated to be activated in phases and completed by late 2019. Utilizing a Progressive Design-Build project delivery method will allow Charlotte Water to work collaboratively with the Design-Build team.
  • Customers will have access to driveways. Some properties may have a temporary blockage as the pipe is installed under street directly in front of the driveway. The contractor will work with residents /business to minimize disruption.
  • Streets will be temporarily restored during construction. Crews will then mill and repave asphalt (12-feet wide).
  • Storm (rain) Water improvements are not part of this effort.

Schedule

Phase                                                                                     End Date

Planning                                                                                 Ongoing
Design/Permitting                                                                Ongoing
Property Easement Acquisition (Real Estate)                  Ongoing
Bid                                                                                           Complete 
Construction                                                                          April  2018 - October 2019


​This project will alleviate wastewater capacity needs identified through Charlotte Water's Capacity Assurance Program.​

​Properties that will be directly affected by construction will be contacted to discuss easement agreements. Areas near construction will be notified before construction.​​​​

​To be determined.

 