Wastewater Replacement Project North Davidson Street at 27th Street

​​​​​​

Project phase

 

 Project updates

  • Charlotte Water has identified a pipe that needs to be repaired and some pipes may need to be replaced. The wastewater pipe is located between 2321 North Davidson Street and 2401 North Davidson Street.
  • Bushes between the businesses may be removed mid-June.
  • Crews will begin repairing/replacing the pipe from mid-June through August.
  • Fences will be replaced.
  • Customers will have access to driveways.
  • The contractor will work with businesses to minimize disruption.
  • North Davidson Street will be open for traffic. A lane may be closed briefly to deliver pipe. Flaggers will assist drivers around the delivery if needed.
  • Updates will be posted on this website and NextDoor.
  • This project will replace pipes that are no longer able to serve the community. Replacing the pipe will reduce the risk of wastewater overflows.

Property owners will be notified in advance. 

​TBD

 