  • Charlotte Water will clean and add a new interior lining to a 54-inch wastewater pipe near Sugar Creek between Rodney Street and Marie Way in Pineville.
  • Crews will reline (rehabilitate) approximately 6,400 linear feet of 54-inch pipe.
  • Work will be on existing easements and right-of-ways.
  • Schedule:
    • Mid-July through September -crews will remove trees and other debris in the easement.
    • Late July through mid-November – crews will clean and inspect the wastewater pipe.
    • September through November – crews will install the new interior lining.
    • October through January – crews will complete work and restore the area.
  • Customers will have access to driveways.
  • The contractor will work with residents /business to minimize disruption.
  • Updates will be posted on this website and NextDoor.​

​Crews clean inside wastewater pipes and install a sock-like lining inside an existing pipe through manholes. Construction area may be in street or backyards.​

​Property owners will be notified in advance. ​

​$3.1 Million

 