Paw Creek Sewer Outfall Replacement Project

​​​​

Project phase

 

 Project updates

  • Frisbee golf course at The Robert L Smith Regional Park will be closed during construction. 
  • This project will alleviate wastewater capacity needs identified through Charlotte Water's Capacity Assurance Program.
  • Existing wastewater pipe (approximately 13,000 feet of 18-inch and 24-inch in diameter pipe) appears to be capacity limited during 2 year and 10-year flow events.
  • Further development in the basin (single family homes on quarter acre lots) indicates that the outfall could experience capacity limitations as development, especially rezoning, continues.
  • Several alternatives for providing additional capacity were considered including a parallel relief sewer and full replacement of the outfall within the same alignment with 30-inch gravity sewer. The full replacement alternative would require bypass pumping. CLTWater decided to go with the parallel replacement sewer of 8-inch to 60-inch in diameter wastewater pipes.

Schedule 

Phase                                                                                      End Date

Planning                                                                                 Complete
Design/Permitting                                                                Complete
Property Easement Acquisition (Real Estate)                  Complete
Bid                                                                                          Summer 2018 or later
Construction                                                                         Fall 2018 to end of 2019
Warranty                                                                               Fall 2020

​Properties that will be directly affected by construction will be contacted to discuss easement agreements. Areas near construction will be notified before construction. ​

​An​ estimated $4.5 million.

 