Myers Park Water Pipe Relocation Project

​​​​​​​

Project phase

 

 Project updates

  • Start in March and may be complete by end of June
  • Crews will start at Lorene and Colony roads (March through the end of July)
  • Abandoning more than 8,000 feet of pipe due to age (some from 1930s)
  • 2 hydrants will be replaced
  • Crews will dig in the street to install a new pipe in most streets.
  • Customers on Roswell and Colony will be moved to an existing pipe under street so construction activity will be limited to replacing service lines.
  • Replacement on Pender completed.
  • Customers can apply for an irrigation connection by clicking here.

Completed - Roswell Avenue, Normandy Road, Lorene Avenue and Colony Road

August - October - Picardy Place, Winding Wood Lane, intersection of Roswell Avenue at Queens Road West, finalize project and restore area

​​​Areas near construction will be notified before construction. There will be planned water outages to move customer’s service. Property owners will be notified in advance. If there is an unplanned water outage, crews will work to fix it immediately.

​​$500,000