Projects

East Forest area neighborhood improvement, phase 2

​​​A 2008 neighborhood bond project​​​​​

Project phase

 

 Project updates

​​​This 2008 neighborhood bond project will provide sidewalk, handicap-accessible ramps and storm drainage upgrades. The area is bounded by Independence Boulevard to the northeast, railroad to the southwest, Sharon Amity to the northwest and Thermal Road to the southeast.  The project comprises two phases:  

  • ​Phase 1 includes sidewalks along parts of Eaglewood, McLaughlin, Pinafore, Lumarka and Peebleridge.  

  • Phase 2 includes sidewalk along Bainbridge, Forest Way, Melba and parts of Knickerbocker and Old Post Road. Storm drainage upgrades will address flooding around the Old Post Road/Mclaughlin Drive area and the Coatbridge Lane/McLaughlin Drive intersection.

​The plans were based on safety, cost, benefits, traffic analysis and an extensive public involvement process. As part of Phase 2, we will be removing a house and installing a detention pond.    

NOTE: Monroe Road is maintained by the North Carolina Department of Transportation (NCDOT), not the City of Charlotte. Please report any maintenance issues for Monroe Road to NCDOT at 1-877-368-4968 during normal business hours. ​​ 

To maintain, stabilize and revitalize the neighborhood through comprehensive infrastructure improvements

​Public meetings were held in August 2007, November 2007, February 2007 and July 2012. You can view meeting minutes, newsletters and postcards associated with this project under "Project documents" on this page.​​

Phase 1: $1.04 million
Phase 2: $2.2 million​

​​​Please note this is the funding amount and includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.​